IMPORTANT ANNOUNCEMENT: The date of submission of all Tender Documents is extended upto 27-03-2025 at 11am instead of 18-03-2025

Welcome to Ambur Economic Development Organisation

Ambur and Vaniyambadi in Tamilnadu is a major leather cluster represented by AMBURTEC/VANITEC contributing a significant share in the country’s leather export but severely handicapped by poor infrastructure, particularly waste water disposal and product development and marketing facilities. In order to maintain its primacy as the largest producer of leather goods and products, and to emerge as an international destination for leather industry, both Amburtec and Vanitec joined and formed the Ambur Economic Development Organization (AEDOL) on 23.07.2001, to take advantage of the Schemes being implemented by the Department Industrial policy &Promotion, GOI., for integrated infrastructure development programme to enable the clusters meet their aim of Zero Liquid Discharge by recycling the treated water, and all other existing environmental standards.

In 2005 we got the sanction from the DIPP for the first upgradation of ZLD system under IIUS (Industrial infrastructure Upgradation Scheme - 2003)at a total project cost of Rs. 6733.75/- lakhs of which the GoI Grant was Rs.4393.54 lakhs. The project was completed in 2010 at a total cost of Rs.9338 Lakhs with the members contribution and term loan from IL & FS.

In 2018 we got the sanction from the DPIIT of ZLD system under IFLADP (Indian Footwear Leather & Accessories Development Programme) at a total project cost of Rs. 13660/- lakhs of which the GoI Grant was Rs.9562 lakhs. The project was completed in 2023 at a total cost of Rs.14,184.21/- Lakhs with the members contribution.

img

MALIGAITHOPE CETP

The Common Effluent Treatment Plant at Maligaithope Sector was established in year 1998 for a capacity of 1100 m3/day. It has 17 member tanneries out of which 12 member tannery are in regular operation now.

img

THUTHIPET CETP

The Common Effluent Treatment Plant at Thuthipet Sector was established in year 1995 a capacity of 2219 m3/day. It has 49 member tanneries out of which 38 are currently operational.

img

VANITEC LTD, VALYAMPET CETP

VANITEC LTD, is a Company that was incorporated in the year 1991 for a capacity of 3342 m3/day. It has 130 member tanneries.

img

SOLAR POWER PLANT

Power is currently sourced from the Tamil Nadu Electricity Board (TNEB) and from in-house Diesel Generating Sets during power outages.

Project Gallery

WHY CHOOSE US ?

    Preparation of Detailed Project Report by ILIFO

    Apprisal of Detailed Project Report

    Appoinment of SPV - AEDOL by DPIIT

    Issue of Tender by aedol for appointment of TA

    Technical Evaluation done by AEDOL

    Work Order issued to TA - ILIFO

    Preparation of Tender Document by
    TA-ILIFO

    Issuance of Tender for execution of works

    Pre-bid Meeting

    Issuance of Addendum to the Tender Document

    Tenders submission by prospective bidders

    Technical Evaluation of Bids by ILIFO

    Obtaining Clarifications on queries raised by ILIFO

    Preparation of Technical Evaluation Report by ILIFO

    Financial Bid Evaluation by ILIFO

    Financial Evaluation Report to AEDOL by ILIFO

    Financial Negotiation with L1 Bidder by CETP, assisted by ILIFO & AEDOL

    Issuance of Work Order by AEDOL after Internal Approval

Infrastructure

No.43/53, Raja Muthiah Road, Periamet, Chennai – 600003. INDIA

044 - 35528648 044 – 42041132